PennEast Pipeline
PERMITTING DASHBOARD PROJECT POSTING DATE: SEPTEMBER 22, 2016PROJECT WEBSITE: http://penneastpipeline.com
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
CANCELLED
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
N/A
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Pipelines
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Federal Energy Regulatory Commission
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Civil Works
Department of the Interior, Fish and Wildlife Service
Description:
PennEast Pipeline (Docket No. CP15-558-000) would provide an additional 1.0 Bcf/d of natural gas transportation service through construction of: (1) 115.1 miles of pipeline from Pennsylvania to New Jersey; (2) 2.1 miles of various lateral pipelines; and (3) a new compressor station.
On December 16, 2021, the Commission issued an order vacating the certificate authorization for the PennEast Pipeline. Under the Commission’s regulations, parties have 30 days to file for rehearing of orders. No parties filed a request for rehearing of the Commission's order.
Project Application and Supporting Documents
- PennEast Pipeline, Project Application, Volume I, FERC Docket No. CP15-558-000 (submitted 09/25/2015). Document located at: https://elibrary.ferc.gov/eLibrary/filelist?accession_Number=20150925-5028.
- PennEast Pipeline, Supporting Documents to Project Application, FERC Docket No. CP15-558-000 (submitted 09/25/2015). Documents located at: https://elibrary.ferc.gov/eLibrary/docinfo?accession_number=20150925-5029.
- Additional Project-related filings and issuances can be found on FERC’s eLibrary website by searching under Docket Nos. CP15-558.
Federal Agency Actions
- Federal Energy Regulatory Commission, Notice of Schedule for Environmental Review of the PennEast Pipeline Project (issued 03/29/2016). Document located at: https://elibrary.ferc.gov/eLibrary/filelist?accession_Number=20160329-3066.
- Federal Energy Regulatory Commission, Draft Environmental Impact Statement (issued 07/22/2016). Document located at: https://www.ferc.gov/draft-environmental-impact-statement-penneast-pipeline-project.
- Federal Energy Regulatory Commission, Notice of Revised Schedule for Environmental Review of the PennEast Pipeline Project (issued 11/08/2016). Document located at: https://elibrary.ferc.gov/eLibrary/filelist?accession_Number=20161108-3025.
- Federal Energy Regulatory Commission, Notice of Revised Schedule for Environmental Review of the PennEast Pipeline Project (issued 1/23/2017). Document located at: https://elibrary.ferc.gov/eLibrary/docinfo?accession_number=20170123-3010.
- Federal Energy Regulatory Commission, Final Environmental Impact Statement (issued 04/07/2017). Document available at: https://cms.ferc.gov/final-environmental-impact-statement-penneast-pipeline-project.
- Federal Energy Regulatory Commission, Order Issuing Certificate (issued 01/19/2018). Document located at: https://elibrary.ferc.gov/eLibrary/filelist?accession_Number=20180119-3110.
- Federal Energy Regulatory Commission, Letter to Project Sponsor on the Status of the Project (issued 11/23/2021). Document located at: https://elibrary.ferc.gov/eLibrary/filedownload?fileid=7124F040-7612-CB59-9BD7-7D4DE2500000.
- Federal Energy Regulatory Commission, Order Vacating Certificate Authorization (issued 12/16/2021). Document located at: https://elibrary.ferc.gov/eLibrary/filedownload?fileid=D29E467F-F6C2-C913-97DF-7DC403B00000.
Status of Mitigation Measures
- Not applicable. On December 16, 2021, the Commission issued an order vacating the certificate authorization for the PennEast Pipeline.
FERC Litigation
- None filed.
Public Meetings and Comment Periods
- There are no planned public meetings or comment periods. On December 16, 2021, the Commission issued an order vacating the certificate authorization for the PennEast Pipeline.
Last updated March 12, 2022
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|