PORTS Technology Campus

PERMITTING DASHBOARD PROJECT POSTING DATE: JUNE 11, 2026

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Planned

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PLANNED

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
PENDING

0 out of 0

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

High-performance computing and advanced computer hardware and software

SECTOR
High-performance computing and advanced computer hardware and software

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Army

LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Regulatory

View FAST-41 Postings by Agencies

Description:

The data center complex will be located on approximately 1,300 acres of private land adjacent to the Department of Energy Portsmouth Site in Pike County, Ohio. The project consists of two data center buildings and their associated infrastructure, including access roads, administrative buildings, substations, laydown yards, and parking infrastructure.