Red River L&D No. 4

PERMITTING DASHBOARD PROJECT POSTING DATE: SEPTEMBER 22, 2016

PROJECT WEBSITE: http://www.nelsonenergy.us/ourprojects.html(link is external)

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/17/2017

3 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Federal Energy Regulatory Commission

LEAD AGENCY
Federal Energy Regulatory Commission

Description:

Red River Lock & Dam No. 4 Hydroelectric Project (Project No. 12757) is a proposal to construct an original 28.1 MW conventional hydropower project at the existing U.S. Army Corps of Engineers' (Corps) Red River Lock and Dam No. 4, which is located on the Red River in Red River Parish, Louisiana.  The proposed project would occupy 135.1 acres of federal land managed by the Corps.  FERC issued a license order for this project on February 17, 2017.

Project Application and Supporting Documents

Federal Agency Actions

FERC Litigation

  • None filed.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.