Royal Slope Solar Project

PERMITTING DASHBOARD PROJECT POSTING DATE: JUNE 02, 2025

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Planned

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PLANNED

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
PENDING

0 out of 0

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Reclamation

View FAST-41 Postings by Agencies

Description:

The Royal Slope Solar Project includes a 260-megawatt (MW) utility-scale solar energy facility and accessory battery energy storage system (BESS, anticipated 260 MW, 4-hour duration), substation, transmission line, and associated facilities on private lands in unincorporated Grant County, Washington. This Project will serve electricity users in Washington, with the target of serving Grant County specifically. The transmission line connecting the solar facility to the existing Bonneville Power Administration Vantage Substation would cross federal land managed by the U.S. Bureau of Reclamation.

Permitting Timetable

Planned Environmental Review and Permitting processes