Samantha Solar
PERMITTING DASHBOARD PROJECT POSTING DATE: NOVEMBER 22, 2024All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PLANNED
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
PENDING
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Land Management
Description:
Balanced Rock Power proposes to construct a 600-megawatt (MW), alternating current (AC) solar photovoltaic (PV) power generating facility with a battery energy storage system (BESS). The Project’s primary purpose is to produce 600-MW of energy annually. The Project site would be located in White Pine County, Nevada on approximately 2,891 acres of lands managed by the U.S. Bureau of Land Management (BLM), approximately 15 miles west of Ely, Nevada. The Project site would be divided into two areas of BLM-managed land adjacent to and on the east and west sides of another proposed solar project. The Project would also include a 5.8-mile transmission interconnection line at either 500 or 345 kV to interconnect the project to the existing Robinson Summit Substation.