Silver Rock Transmission Project
PERMITTING DASHBOARD PROJECT POSTING DATE: DECEMBER 08, 2025All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/29/2028
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Electricity Transmission
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Land Management
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Department of Defense
Department of the Interior, Bureau of Reclamation
Description:
Silver Rock Transmission proposes to construct a large-scale high voltage transmission line to cross approximately 330-miles of public land to help facilitate BLM's geothermal leasing activities in eastern Nevada and western Utah by providing a viable transmission path to market for next-generation geothermal developments, thereby supporting federal leasing objectives and unlocking access to high-capacity baseload resources. The project would be constructed to transfer a nominal voltage of up to 600 kilovolts (kV) located within a siting corridor of approximately 1,000 feet.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|