South Fort Meade – South of SR 64 Parcels
PERMITTING DASHBOARD PROJECT POSTING DATE: JULY 22, 2025PROJECT WEBSITE: https://mosaicfloridaphosphate.com/communities/hardee-county/south-fort-meade/
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/02/2027
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Mining
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Regulatory
View FAST-41 Postings by Agencies
Description:
Mosaic Fertilizer, LLC (Mosaic) plans to extend their existing mine to extract phosphate ore from known mineable reserves near their South Fort Meade (SFM) beneficiation plant. Mining will be on portions of an approximately 2,000-acre tract of land in Hardee County, Florida. The land abuts the South Fort Meade Mine - Eastern Extension which lies to the south of State Road 64 (SR 64). Mining involves a number of steps: after land clearing and site preparation, the phosphate ore is extracted, and the land is reclaimed to state standards. The phosphate ore will be beneficiated at Mosaic’s existing SFM beneficiation plant.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|