Sparrows Point Container Terminal

PERMITTING DASHBOARD PROJECT POSTING DATE: SEPTEMBER 25, 2023

PROJECT WEBSITE: Sparrows Point Container Terminal

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/16/2025

6 out of 6

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Ports and Waterways

SECTOR
Ports and Waterways

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Army

LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Regulatory

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Army

Department of the Army, US Army Corps of Engineers - Section 408

Description:

The proposed Sparrows Point Container Terminal (SPCT) project will be located on 330 acres within the existing Tradepoint Atlantic industrial development site in Baltimore County, Maryland, southeast of the city of Baltimore.  SPCT will expand the Baltimore service for Mediterranean Shipping Company, the world's largest container carrier, which will create thousands of additional port related jobs and dramatically enhance and support the long-term growth of the Port of Baltimore and the state of Maryland. The SPCT is also the next major phase of redevelopment of the former Sparrows Point Steel Mill, an effort initiated in 2014 by Tradepoint Atlantic.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete