Sunrise Wind Farm

PERMITTING DASHBOARD PROJECT POSTING DATE: SEPTEMBER 16, 2020

PROJECT WEBSITE: https://www.boem.gov/Sunrise-Wind

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/21/2024

5 out of 12

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Environmental Protection Agency

Environmental Protection Agency

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Interior

Department of the Interior, National Park Service

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Description:

Sunrise Wind LLC (Sunrise Wind) proposes to construct, operate and maintain an offshore wind farm to be located approximately 18.5 statute miles (mi) (16.1 nautical miles [nm], 29.8 kilometers [km]) south of Martha’s Vineyard, Massachusetts, and approximately 30 mi (26.1 nm, 48.2 km) east of Montauk, New York (NY). The majority of the Project would be located in federal waters in the designated Bureau of Ocean Energy Management (BOEM) Renewable Energy Lease Area OCS-A 0487.

Update:

The Executive Director granted a BOEM request to extend the Construction and Operations Plan (COP) completion date on November 16, 2021. The Executive Director determination is posted here.

The Executive Director granted a BOEM request to extend the NEPA, COP, Section 106, MMPA (NOAANMFS), Sections 10/404/408 (USACE), NPS Permit (NPS), Clean Water Act Section 402 (EPA), and OCS Air Permit (EPA) completion dates on June 6, 2023. The Executive Director determination is posted here.

The Executive Director granted a BOEM request to extend the COP, NPS, Section 10/404, Section 408, OCS Air Permit, NPDES completion dates on Feb 2, 2024. The Executive Director determination is posted here.

 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete