USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

SunZia Southwest Transmission Project

PERMITTING DASHBOARD PROJECT POSTING DATE: JULY 29, 2021

PROJECT WEBSITE: SunZia Project Website

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/24/2023

6 out of 6

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Electricity Transmission

SECTOR
Electricity Transmission

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Description:

The SunZia Project includes two nominal 500-kV transmission lines located on federal, state, and private lands between central New Mexico and central Arizona. The approximately 550-mile-long transmission line route originates at the planned SunZia East Substation in Torrance County, New Mexico, and terminates near the existing Saguaro substation and the existing Pinal Central Substation, both in Pinal County, Arizona. The SunZia Project is located in Socorro, Sierra, Luna, Grant, Hidalgo, and Torrance counties in New Mexico and Graham, Greenlee, Cochise, Pinal, and Pima counties in Arizona.

The SunZia Project will be constructed in two phases and ultimately include two, new, single-circuit, 500 kV transmission lines with the intent of locating both within a single 400-foot-wide right-of-way, where possible. Only one of the two 500-kV circuits will be constructed in Phase 1 and the planned in-service date for the first transmission line is 2025. The first transmission line would be a direct-current (DC) line and the second transmission line would be an alternating-current (AC) line.

Update:

The Executive Director granted a BLM's request to extend the Section 106 consultation "Section 106 Review" completion date because route changes for the Project require modifications to the programmatic agreement needed to conclude the Section 106 consultation. The Executive Director determination is posted here.

The Executive Director granted a BLM's request to extend the Endangered Species Act "Endangered Species Act (ESA)," completion date because because, FWS asked BLM to submit additional information to ensure a complete consultation package that would enable FWS to complete formal consultation under the ESA. The Executive Director determination is posted here.

 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete