USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Swan Lake North Pumped Storage

PERMITTING DASHBOARD PROJECT POSTING DATE: SEPTEMBER 22, 2016

PROJECT WEBSITE: http://www.ryedevelopment.com

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/17/2019

6 out of 6

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Federal Energy Regulatory Commission

LEAD AGENCY
Federal Energy Regulatory Commission

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Interior

Department of the Interior, Bureau of Land Management

Department of the Interior

Department of the Interior, Bureau of Reclamation

Description:

Swan Lake North Pumped Storage (Project No. 13318) is a proposal to construct an original, closed-loop pumped storage project that would provide 393 MW of generation capacity in Oregon.  The proposed project would consist of, among other facilities, an upper and lower reservoir with active storage capacities of 2,562 and 2,581 acre-feet, respectively, a high-pressure penstock, three low-pressure penstocks, a powerhouse, a substation, and a 32.8-mile-long, 230-kilovolt transmission line. 

Project Application and Supporting Documents

Federal Agency Actions

FERC Litigation

  • None filed.

 

Last updated November 22, 2019

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete