Texas Gateway Project
PERMITTING DASHBOARD PROJECT POSTING DATE: JULY 10, 2026PROJECT WEBSITE: Texas Gateway Project Website
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/14/2028
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Pipelines
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Federal Energy Regulatory Commission
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Interior, Bureau of Land Management
Description:
The Project consists of the construction of a new approximately 155-mile-long natural gas pipeline comprised of 36-inch and 42-inch diameter pipe segments originating in Carthage, Texas and terminating in Beauregard Parish, Louisiana. The Project includes three new delivery meter and regulator stations, one new compressor station along Gulf South Pipeline Company’s existing Index 129 pipeline in San Jacinto County, Texas, along with expanding two existing compressor stations in Panola and Sabine Counties, Texas.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|