USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Antler Copper Project

PROJECT WEBSITE: Antler Copper Mine and Powerline Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/30/2026

0 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Mining

SECTOR
Mining

transparency icon

CATEGORY
Project Category FAST-41 Transparency Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

Description:

Antler Operations Inc. has submitted a Mine Plan of Operations (MPO) to construct facilities on the surface of public lands managed by the BLM Kingman Field Office for subsurface mining of copper and related minerals. The proposed project ancillary facilities include a waterline, a haul road, and fencing; and a proposed 11.6-mile (3.9 on public land) 69 kilovolt (kV) power transmission line, in portions of Sections 4 and 7, T17N, R16W, and Sections 10, 12, and 16, T17N, R17W, Gila and Salt River Meridian (Project Area).

This project is posted in the interest of transparency and response to Executive Order 14241.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete