La Jara Mesa
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/03/2028
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

SECTOR
Mining
CATEGORY
Project Category
FAST-41 Transparency Projects
LEAD AGENCY
Department of Agriculture, US Forest Service
Description:
This project proposes development of underground uranium mining and surface support facilities at the La Jara Mesa property at Mt. Taylor near Grants, NM.
This project is posted in the interest of transparency and response to Executive Order 14241. A permitting timetable will be published for this project on or before May 16, 2025.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|