Lisbon Valley Copper Project

PROJECT WEBSITE: Lisbon Valley Copper Mining Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/24/2025

6 out of 6

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Mining

SECTOR
Mining

transparency icon

CATEGORY
Project Category FAST-41 Transparency Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

Description:

Lisbon Valley Mining Company, LLC (LVMC) currently mines copper ore from an open pit mine on 4,480 acres in San Juan County, Utah. LVMC submitted a Plan of Operations Modification to the Bureau of Land Management to expand open pit and beneficiation operations, and to initiate the extraction of copper through a method of in-situ recover into an adjoining area. Additions would include a new open pit, waste rock storage area, process ponds, and in-situ recovery wells in a proposed 5,430 acres. Estimated surface disturbance contained in the Plan of Operations Modification is 1,190 acres. In addition to BLM’s analysis, the project would also require a pending aquifer exemption from the Environmental Protection Agency to allow fluids to be injected underground for the in-situ recovery process.

This project is posted in the interest of transparency and response to Executive Order 14241. 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete