Polaris Exploration Project

PROJECT WEBSITE: Aurora Mining District -Polaris Exploration Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/31/2026

3 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Mining

SECTOR
Mining

transparency icon

CATEGORY
Project Category FAST-41 Transparency Projects

Department of Agriculture

LEAD AGENCY
Department of Agriculture, US Forest Service

View Postings by Agencies

Description:

Temporary construction of up to 25 miles of new and/or reconstruction of previously reclaimed roads; construction of 250 drill sites; exploration drilling activities for gold resources, and reclamation of all proposed disturbances on Forest Service land.

This project is posted in the interest of transparency and response to Executive Order 14241. 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete