Schell Creek

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/02/2026

1 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Mining

SECTOR
Mining

transparency icon

CATEGORY
Project Category FAST-41 Transparency Projects

Department of Agriculture

LEAD AGENCY
Department of Agriculture, US Forest Service

Description:

The Muncy Creek Exploration Plan of Operations proposes mineral exploration for copper, zinc, molybdenum, and silver in the Ely Ranger District of the Humboldt-Toiyabe National Forest and on private lands in White Pine County Nevada. The larger, proposed project boundary (claim area) covers a total of 97 acres, 75 acres on National Forest System lands and 22 acres on private lands.

Exploration activities are proposed to occur over a ten-year period in phases and include drill pad construction, exploration drilling, road construction, and road maintenance. Phase I includes the construction of six drill sites, and nine additional drill sites are proposed over additional phases for a total of 15 drill sites. There are 9.1 acres of disturbance and 2.3 miles of road are proposed on National Forest System lands. Total project disturbance on public and private lands would not exceed 15 acres and 4.1 miles of road.

This project is posted in the interest of transparency and response to Executive Order 14241.

  

 

 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete