Sheep Creek Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/11/2027

0 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Mining

SECTOR
Mining

transparency icon

CATEGORY
Project Category FAST-41 Transparency Projects

Department of Agriculture

LEAD AGENCY
Department of Agriculture, US Forest Service

View Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

The Sheep Creek project is located in the Bitterroot National Forest, West Fork Ranger District  in Ravalli County, Montana approximately 40 miles southwest of Darby, Montana.  The project is near the Montana-Idaho border in the West Fork of the Bitterroot river drainage. The Sheep Creek project  is focused on the exploration of gallium, samarium, scandium, neodymium, praseodymium and other economically viable heavy rare earth elements. This exploration project includes activities to maintain existing roads (approx. ¾ miles), secure and stabilize three existing adits, exploratory drilling and extraction underground inside adits, exploration drilling on surface with up to 10 boreholes with associated pads and road work, and other ore sampling activities.  

This project is posted in the interest of transparency and response to Executive Order 14241.  This permitting timetable will be updated when the project sponsor submits an application for an authorization.  The initial permitting timetable reflects the agency’s best estimates based on available information, but is likely to vary widely, depending on receipt of a complete application.

 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete