Taylor Shellfish Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/31/2028

0 out of 5

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Water Resources

SECTOR
Water Resources

transparency icon

CATEGORY
Project Category FAST-41 Transparency Projects

Department of Commerce

LEAD AGENCY
Department of Commerce, National Oceanic and Atmospheric Administration

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

Taylor Shellfish Farms is pursuing Incidental Take Permits (ITPs) under Section 10 of the Endangered Species Act (ESA) for its shellfish farming operations within marine tideland, subtidal lands, and associated riparian areas in North Sound, South Sound, Hood Canal, and Willapa Bay (Puget Sound and Willapa Bay), excluding Grays Harbor, in Washington state.

Taylor is developing a Habitat Conservation Plan (HCP), a required component of their ITP application under ESA Section 10. The HCP would address conservation measures to minimize and mitigate, to the maximum extent practicable, the impact of any incidental take associated with Taylor Shellfish Farms' activities on all covered species.

This project is posted in the interest of transparency.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete