The entire FAST-41 Initiation Notice is marked as confidential business information and is therefore not available for public posting.
The Environmental Impact Statement and related documents will be posted on the Department of Energy’s website once they are available.
The Title 17 loan application is marked as confidential business information and is therefore not available for public posting.
These will be identified in the Draft Environmental Impact Statement.
None.
The DEIS Public Comment Period is open January 17 to March 3, 2025
DEIS Public Meetings (Central Time) are scheduled as follows:
February 10, 2025 - 4 – 6 p.m., Dodge City Public Library, 1001 N. 2nd Ave., Dodge City, KS 67801
February 11, 2025 - 4 – 6 p.m., Holiday Inn Express, 2175 Lincoln St., Concordia, KS 66901
February 12, 2025 - 4 – 6 p.m., St. Joseph Museum, Jackie Lewin Conference Roon, 3406 Frederick Ave. St. Joseph, MO 64506
February 13, 2025 - 4 – 6 p.m., La Bella Casa Event Center, 5 South Main St., Carrollton, MO 64633
Virtual Meetings (Central Time):
February 19, 2025 - 11 a.m. – 1 p.m.
February 20, 2025 - 4 - 6 p.m.
For more information, please visit: EIS-0554: Grain Belt Express Transmission Line | Department of Energy
None at this time.