USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

FAST-41 Postings by Agencies for Kitty Hawk South Offshore Wind Project

Department of the Army (Posted on: )

FAST-41 Initiation Notice

Provided by lead agency.

Application and Supporting Documents

Not available at this time.

Information on the status of mitigation measures

No decisions on mitigation requirements made at this time.

Description of the status of any litigation

N/A

Information about project-related public meetings, public hearings, and public comment periods

Not available at this time.

Description of any Federal agency action taken or decision made that materially affects the status of the project

No decision/final action taken at this time.

Fish and Wildlife Service (Posted on: )

FAST-41 Initiation Notice

BOEM has posted the FIN.

Application and Supporting Documents

None at this time.

Information on the status of mitigation measures

None at this time.

Description of the status of any litigation

NA

Information about project-related public meetings, public hearings, and public comment periods

None at this time.

Description of any Federal agency action taken or decision made that materially affects the status of the project

None at this time.

Environmental Protection Agency (Posted on: )

FAST-41 Initiation Notice

Posted by lead agency

Application and Supporting Documents

Posted at this link when available:

Outer Continental Shelf permit: https://www.epa.gov/caa-permitting

Information on the status of mitigation measures

N/A

Description of the status of any litigation

No EPA litigation information at this time

Information about project-related public meetings, public hearings, and public comment periods

Posted at this link when available:

Outer Continental Shelf permit: https://www.epa.gov/caa-permitting

Description of any Federal agency action taken or decision made that materially affects the status of the project

Posted at this link when available:

Outer Continental Shelf permit: https://www.epa.gov/caa-permitting

Bureau of Ocean Energy Management (Posted on: )

Application and Supporting Documents

Will be available on a BOEM-website once the site is developed.

Information on the status of mitigation measures

Will be determined in the Record of Decision (ROD).  When complete, the ROD will be posted on the website noted above.

Description of the status of any litigation

None.

Information about project-related public meetings, public hearings, and public comment periods

Will be available on a BOEM-website once the site is developed.

Description of any Federal agency action taken or decision made that materially affects the status of the project

Will be available on a BOEM-website once the site is developed.

National Oceanic and Atmospheric Administration (Posted on: )

FAST-41 Initiation Notice

Posted by lead agency

Application and Supporting Documents

NA - to be updated when NMFS receives information

Information on the status of mitigation measures

NA

Description of the status of any litigation

NA

Information about project-related public meetings, public hearings, and public comment periods

NA

Description of any Federal agency action taken or decision made that materially affects the status of the project

NA