The project sponsor filed an application under section 7 of the Natural Gas Act on September 12, 2025. The application and other supporting documents can be found under docket numbers CP25-547 and CP25-549 in the Commission's eLibrary system.
Commission staff will include any staff-recommended mitigation measures in this section after issuance of the draft and final National Environmental Policy Act documents.
There is no active litigation on the Commission's certificate proceedings.
Information on the timing of project-related comment periods and public meetings will be added to this section as it becomes available.
- On September 25, 2025, the Commission issued a notice with information on how to become involved in the Commission's review process, including filing comments.
- On November 14, 2025, the Commission issued a notice establishing a deadline for filing comments on the scope of issues to address in the Environmental Impact Statement.
- On September 25, 2025, the Commission issued a Notice of Application.
- On November 14, 2025, the Commission issued a Notice of Intent to Prepare an Environmental Impact Statement.