Kulning Wind Energy Project
PERMITTING DASHBOARD PROJECT POSTING DATE: SEPTEMBER 29, 2021PROJECT WEBSITE: Kulning Wind Energy
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
CANCELLED
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
N/A
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Land Management
View FAST-41 Postings by Agencies
Description:
The Kulning Wind Energy Project (project) proposed by Crescent Peak Renewables (project sponsor) is located on federal lands administered by the U.S. Bureau of Land Management (BLM) in Clark County, Nevada.
The proposed project includes a 308-MW wind energy generation plant consisting of up to 68 wind turbine generators, a project substation including switchgear and battery energy storage equipment, accompanying ancillary infrastructure, and a 29-mile transmission line to Sloan Canyon Switching Station.
On March 21, 2023, President Biden signed a proclamation establishing the Avi Kwa Ame National Monument. The entirety of the proposed Kulning Wind Energy Project is within the boundary of the national monument.
On August 10, 2023, Crescent Peak Renewables submitted a request to the BLM Las Vegas Field Office to withdraw the applications for the project.
On August 13, 2023, BLM formally accepted the request to withdraw the applications for the project.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|