USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

FAST-41 Postings by Agencies for NANA Regional Broadband Network (NRBN)

National Telecommunications and Information Administration (Posted on: )

FAST-41 Initiation Notice

Project Information:

  • Project Title: NANA Regional Broadband Network (NRBN)
  • Sector: Broadband
  • Type: Rural Broadband Infrastructure

Project Location Address:

  • Country: United States
  • Street Address 1: 100 Shore Ave
  • City: Kotzebue
  • State: Alaska
  • Zip: 99752
  • County: Alaska
  • Street Address 2: 909 W 9th
  • City: Anchorage
  • State: Alaska
  • Zip: 99501
  • County: AK

Coordinates:

  • Latitude: 67.00801012
  • Longitude: -160.03196494

Project Sponsor Contact Information

  • Company Name/Agency: NANA Regional Corporation, Inc.
  • Project Sponsor: NANA Regional Corporation, Inc.
  • Street Address: 909 W 9th
  • City: Anchorage
  • State: Alaska
  • Zip: 99501
  • POC Name: Jason Louvier
  • POC Title: Project Superintendent, NANA Regional Broadband Network
  • POC Work Phone: 907-265-4115
  • POC Email Address: jason.louvier@nana.com

Alternative Point of Contact (Optional)

  • Company Name/Agency: NANA Regional Corporation, Inc.
  • Project Sponsor: NANA Regional Corporation, Inc.
  • Street Address: 909 W 9th
  • City: Anchorage
  • State: Alaska
  • Zip: 99501
  • POC Name: Travis Stubblefield
  • POC Title: Director of OSP Engineering and Field Operations
  • POC Work Phone: 907-265-4331
  • POC Email Address: Travis.Stubblefield@nana.com

Project Purpose

NANA Regional Corporation, Inc. (NANA) has secured funding from the U.S. Department of Commerce, National Telecommunications and Information Administration (NTIA), to implement a high-speed broadband network in the NANA region under the Tribal Broadband Connectivity Program (TBCP). The NANA Region Broadband Project stands as one of the largest infrastructure initiatives in the region, aiming to provide affordable and reliable high-speed broadband access to over 7,000 individuals currently unserved by NTIA/FCC standards.

The primary objective is to install a future-proof, fiber-based broadband network capable of bridging the digital divide and providing high-speed internet services to eight unserved Alaska Native Villages. This project will improve access to education, healthcare, government services, and economic opportunities, while also enhancing public safety through improved communication infrastructure.

Project Description

The proposed ~725-mile fiber optic cable route will consist of terrestrial ground-laid, subsea, trenched, and aerial cable to connect 10 villages to the broadband Point of Presence (PoP) in Kotzebue. Key materials include fiber optic cable (FOC), vaults, hardened splice cases, poles for crossings, and network equipment at each village. The installation will primarily consist of ground-laid cable expected to self-bury over time.

Technical and Financial Ability

NANA manages a portfolio of companies with annual revenues of $1.8B and 10,000 employees, providing services in telecommunications, IT, construction, and more. These companies have completed numerous telecommunication projects, including submarine fiber optic cables, microwave radio relay networks, and satellite ground stations.

NANA’s teams include licensed professional engineers, telecommunications experts, construction professionals, and more, all equipped to handle the demands of this project.

Summary of Financing, Reviews, and Authorizations

  • Award Information:
    • Award Number/FAIN: NT23TBC0290014-T1-01 Revision 1 / NT23TBC0290014 / Mod 1
    • Award Type: Grant
    • Total Cost: $65,168,000
  • Environmental Assessment and NEPA Review: NTIA Lead Agency
  • Relevant Resource Agencies: Bureau of Land Management, U.S. Fish and Wildlife Service, U.S. Army Corps of Engineers, National Park Service, and others regarding permitting and approvals.

Project Assessment

This broadband infrastructure project meets the eligibility requirements for the qualifying industry sector, Broadband, under the Tribal Sponsored Pathway. The project is subject to NEPA and is sponsored by an Alaska Native Corporation, NANA Regional Corporation, Inc., on lands owned or under the jurisdiction of the entity that sponsors the activity.

Submitter Contact Information

  • Name: Jason Louvier
  • Title: Project Superintendent, NANA Regional Broadband Network
  • Work Phone: 907-265-4115
  • Email: Jason.Louvier@nana.com
 
Application and Supporting Documents

N/A at this time.

Information on the status of mitigation measures

N/A at this time.

Description of the status of any litigation

N/A at this time.

Information about project-related public meetings, public hearings, and public comment periods

N/A at this time. 

Description of any Federal agency action taken or decision made that materially affects the status of the project

On February 27, 2025, NTIA received the FAST-41 Initiation Notice (FIN) for the NANA Regional Broadband Network Tribal project in Alaska. 

On March 10, 2025, NTIA determined that the project qualifies for FAST-41 coverage.  

On March 11, 2025, the NANA Regional Broadband Network project was added to the FAST-41 Permitting Dashboard:  https://www.permits.performance.gov/permitting-project/fast-41-covered-projects/nana-regional-broadband-network-nrbn 

 

Fish and Wildlife Service (Posted on: )

FAST-41 Initiation Notice

Lead agency has provided this.

Application and Supporting Documents

SF299 received on March 28th, 2025; FWS responded on May 22nd, 2025 with additional information requested.

Information on the status of mitigation measures

None at this time.

Description of the status of any litigation

None at the time.

Information about project-related public meetings, public hearings, and public comment periods

None at this time.

Description of any Federal agency action taken or decision made that materially affects the status of the project

Not at this time.

National Oceanic and Atmospheric Administration (Posted on: )

FAST-41 Initiation Notice

Posted by lead agency

Application and Supporting Documents

Link to the Environmental Consultation Organizer (ECO) where information about the EFH consultation may be accessed when available:

https://www.fisheries.noaa.gov/resource/tool-app/environmental-consultation-organizer-eco

Information on the status of mitigation measures

NA

Description of the status of any litigation

NA

Information about project-related public meetings, public hearings, and public comment periods

NA

Description of any Federal agency action taken or decision made that materially affects the status of the project

NA

Bureau of Land Management (Posted on: )

FAST-41 Initiation Notice

Lead agency provided this.

Application and Supporting Documents

Lead agency provided this.

Information on the status of mitigation measures

Lead agency provided this.

Description of the status of any litigation

Lead agency provided this.

Information about project-related public meetings, public hearings, and public comment periods

Lead agency provided this.

Description of any Federal agency action taken or decision made that materially affects the status of the project

SF299 received on March 28, 2025; BLM responded on May 14, 2025 with additional information requested.

US Army Corps of Engineers - Regulatory (Posted on: )

FAST-41 Initiation Notice

Posted by Lead Federal Agency

Application and Supporting Documents

No application submitted at this time. 

The Alaska District Regulatory Website is located here:  https://www.poa.usace.army.mil/Missions/Regulatory.aspx

Information on the status of mitigation measures

No available information at this time.

Description of the status of any litigation

None.

Information about project-related public meetings, public hearings, and public comment periods

None scheduled at this time.  

Description of any Federal agency action taken or decision made that materially affects the status of the project

No actions or decisions at this time.