New England Wind
PERMITTING DASHBOARD PROJECT POSTING DATE: MARCH 15, 2021All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/22/2024
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of Commerce, National Oceanic and Atmospheric Administration
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Interior, Fish and Wildlife Service
Environmental Protection Agency
Description:
Update: In October 2021, the project name changed from Vineyard Wind South to New England Wind to reflect restructuring of the project’s parent companies (for more information, see Vineyard Wind’s September 21, 2021 press release).
New England Wind is the proposal to develop offshore renewable wind energy facilities in BOEM Lease Area OCS-A 0534 along with associated offshore and onshore cabling, onshore substations, and onshore operations and maintenance (O&M) facilities. Park City Wind LLC, a wholly owned subsidiary of Avangrid Renewables, LLC, is the Proponent and would be responsible for the construction, operation, and decommissioning of New England Wind. New England Wind will be developed in two Phases. If approved, Phase 1, also known as the Park City Wind project, will be developed in the northeastern portion of Lease Area OCS-A 0534. Phase 2, also known as Commonwealth Wind, will be located southwest of Phase 1.
The Executive Director granted a Bureau of Ocean Energy Management (BOEM) request to extend the NEPA, COP, Section 106, Sections 10/404, and OCS air permit actions completion date on May 10, 2023. The Executive Director determination is posted here.
The Executive Director granted a Bureau of Ocean Energy Management (BOEM) request to extend the Section 106 actions completion date on Nov 22, 2023. The Executive Director determination is posted here.
The Executive Director granted a Bureau of Ocean Energy Management (BOEM) request to extend the COP, Section 10/404 and OCS Air Permit actions completion date on Jan 12, 2024. The Executive Director determination is posted here.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|