Alkali Creek Reservoir Project
PROJECT WEBSITE: Alkali Creek Reservoir Project
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/31/2021
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Water Resources
CATEGORY
Project Category
Other Projects
LEAD AGENCY
Department of the Interior, Bureau of Land Management
Other Agencies with Actions or Authorizations:
Wyoming
Department of the Army, US Army Corps of Engineers - Regulatory
Description:
The State of Wyoming Water Development Commission (WWDC) proposes to construct a 294-acre reservoir on Alkali Creek and ancillary facilities across public and private land near Hyattville, Wyoming. The reservoir would impound approximately 7,994 acre-feet of water under normal conditions, and 9,872 acre-feet when under flood conditions. The reservoir would provide late-season irrigation water for portions of the Nowood River Watershed. The irrigation pool would be available either directly or through exchange for irrigation water.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|