USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Commonwealth LNG Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/14/2024

10 out of 12

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Pipelines

SECTOR
Pipelines

Project Category

CATEGORY
Project Category Other Projects

Federal Energy Regulatory Commission

LEAD AGENCY
Federal Energy Regulatory Commission

Other Agencies with Actions or Authorizations:

Federal Energy Regulatory Commission

Federal Energy Regulatory Commission, Office of Energy Projects

Department of Energy

Department of Energy

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of Homeland Security

Department of Homeland Security, US Coast Guard

Description:

Commonwealth LNG, LLC proposes to construct and operate a new LNG export facility and accompanying natural gas pipeline (Docket No. CP19-502-000) on the west side of the Calcasieu Ship Channel at its entrance to the Gulf of Mexico.  The LNG export facility would consist of six natural gas liquefaction trains (with nominal liquefaction and production capacities of 1.4 million tonnes per annum each), six LNG storage tanks (with storage capacities of 40,000 cubic meters each), and one marine berth capable of accommodating LNG carriers with capacities up to 216,000 cubic meters.  Commonwealth would construct a 30-inch-diameter natural gas pipeline from the LNG export facility, extending 3.04 miles north to interconnect with existing natural gas pipelines within Cameron Parish, Louisiana.

 

Last updated December 9, 2022

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete