Commonwealth LNG Project
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/14/2024
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Pipelines
CATEGORY
Project Category
Other Projects
LEAD AGENCY
Federal Energy Regulatory Commission
Other Agencies with Actions or Authorizations:
Federal Energy Regulatory Commission, Office of Energy Projects
Department of Energy
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Army, US Army Corps of Engineers - Civil Works
Department of Commerce, National Oceanic and Atmospheric Administration
Department of the Interior, Fish and Wildlife Service
Department of Homeland Security, US Coast Guard
Description:
Commonwealth LNG, LLC proposes to construct and operate a new LNG export facility and accompanying natural gas pipeline (Docket No. CP19-502-000) on the west side of the Calcasieu Ship Channel at its entrance to the Gulf of Mexico. The LNG export facility would consist of six natural gas liquefaction trains (with nominal liquefaction and production capacities of 1.4 million tonnes per annum each), six LNG storage tanks (with storage capacities of 40,000 cubic meters each), and one marine berth capable of accommodating LNG carriers with capacities up to 216,000 cubic meters. Commonwealth would construct a 30-inch-diameter natural gas pipeline from the LNG export facility, extending 3.04 miles north to interconnect with existing natural gas pipelines within Cameron Parish, Louisiana.
Last updated December 9, 2022
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|