USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Dow Chemical Company's Harris Reservoir Expansion EIS

PROJECT WEBSITE: https://www.swg.usace.army.mil/Business-With-Us/Regulatory/Special-Projects-Env…

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/20/2023

4 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Water Resources

SECTOR
Water Resources

Project Category

CATEGORY
Project Category Other Projects

Department of the Army

LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Regulatory

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

The Corps Galveston District prepared an environmental impact statement (EIS) for the proposed Harris Reservoir Expansion Project (Project) located in Brazoria County, Texas. The proposed Project would include the construction of a 1,929-acre impoundment with a nominal storage capacity of 50,000 acre-feet, an intake and pump station to divert Dow’s existing surface water rights from the Brazos River, an outlet to Oyster Creek, and an emergency spillway. The Project would also include floodplain enhancements on Oyster Creek, stream restoration, and temporary construction staging and laydown areas. The proposed Project site is located between the Brazos River and Oyster Creek approximately 8 miles northwest of the City of Angleton in Brazoria County, Texas.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete