Eagle Shadow Mountain Solar Project

PROJECT WEBSITE: Eagle Shadow Mountain Solar Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/30/2020

5 out of 5

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category Other Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Indian Affairs

Description:

The U.S. Bureau of Indian Affairs (BIA) and the Moapa Band of Paiute Indians is preparing the Draft Environmental Impact Statement (EIS) for the Eagle Shadow Mountain Solar Project. The Project will utilize photovoltaic (PV) technology and have a capacity of 300 MW 2,200 acre lease area. It will be located within the Moapa River Indian Reservation in Clark County, Nevada, west of Interstate 15 and approximately 40 miles northeast of Las Vegas. The project also includes an approximately 12.5-mile long electric transmission line that would cross Tribal lands, Tribal lands administered by BLM, federal lands administered by the BLM, and private lands owned by NV Energy.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete