Leavenworth National Fish Hatchery Surface Water Intake Fish Screens and Fish Passage Project
PROJECT WEBSITE: https://www.usbr.gov/pn/programs/leavenworth/swisp/index.html
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/10/2021
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Water Resources
CATEGORY
Project Category
Other Projects
LEAD AGENCY
Department of the Interior, Bureau of Reclamation
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Department of the Army, US Army Corps of Engineers - Regulatory
Description:
Reclamation proposes to rehabilitate, replace, and modernize the LNFH surface water intake and delivery system on Icicle Creek near Leavenworth, Washington. The U.S. Fish and Wildlife Service operates LNFH under a funding agreement with Reclamation.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|