USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

MVP Southgate CP19-14

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Paused

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PAUSED

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

4 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Pipelines

SECTOR
Pipelines

Project Category

CATEGORY
Project Category Other Projects

Federal Energy Regulatory Commission

LEAD AGENCY
Federal Energy Regulatory Commission

Other Agencies with Actions or Authorizations:

Federal Energy Regulatory Commission

Federal Energy Regulatory Commission, Office of Energy Projects

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

On June 18, 2020, the Commission issued a certificate order authorizing the project sponsor to construct and operate the MVP Southgate Project, approximately 75.1 miles of natural gas pipeline and associated aboveground facilities in Pittsylvania County, Virginia, and Rockingham and Alamance Counties, North Carolina.  On December 29, 2023, the project sponsor filed a letter with the Commission stating that it is pursuing a redesigned project.  As noted in the letter, the project sponsor has yet to finalize the scope and timeframe of the redesigned project and “is evaluating the permitting and regulatory roadmap for the project . . . and will provide additional information to the Commission and other applicable permitting agencies as it continues with project development.” 

Last updated January 31, 2024.

 

 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete