MVP Southgate CP19-14

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/18/2020

4 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Pipelines

SECTOR
Pipelines

Project Category

CATEGORY
Project Category Other Projects

Federal Energy Regulatory Commission

LEAD AGENCY
Federal Energy Regulatory Commission

Description:

On June 18, 2020, the Commission issued a certificate order in Docket No. CP19-14-000 authorizing the project sponsor to construct and operate the MVP Southgate Project, including approximately 75 miles of natural gas pipeline and associated aboveground facilities in Pittsylvania County, Virginia, and Rockingham and Alamance Counties, North Carolina.  On February 3, 2025, the project sponsor filed an application in Docket No. CP25-60-000 requesting to amend the certificate for the MVP Southgate Project issued by the Commission in Docket No. CP19-14-000.  Among other changes, the project sponsor proposed to reduce the length of the pipeline route from 75 miles to 31.3 miles.  On December 18, 2025, the Commission issued an order amending the certificate.

 

 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete