Pine Valley Water Supply

PROJECT WEBSITE: https://eplanning.blm.gov/eplanning-ui/project/1503915/510

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/01/2026

3 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Water Resources

SECTOR
Water Resources

Project Category

CATEGORY
Project Category Other Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

Description:

The Central Iron County Water Conservancy District (CICWCD) filed an SF-299 Application for Transportation and Utility Systems and Facilities on Federal Lands with the Bureau of Land Management's (BLM) Cedar City Field Office (CCFO) for a proposed buried water pipeline project and related appurtenances (Proposed Action); referred to as the Pine Valley Water Supply project (PVWS). The PVWS project would consists of construction, operation and maintenance of well and pumping facilities, solar power generation site and facility, water transmission pipeline and other related appurtenances, a water storage facility and the terminus of the pipeline that would connect wells in Pine Valley to the Cedar Valley system.

At the Applicant's request, BLM resumed work on this project on May 19, 2025.

 

 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete