Southern Bighorn Solar Projects

PROJECT WEBSITE: https://southernbighornsolar.com

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/14/2021

2 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category Other Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Indian Affairs

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

The proposed action is the review and approval of leases that would result in the construction, operation and maintenance, and eventual decommissioning of solar photovoltaic electricity generation and battery storage facilities. This consists of two projects and would have a combined capacity of up to 400 MW of energy.

•        Project one – up to 300 MW

•        Project two – up to 100 MW

The projects would be constructed on up to 3,600 acres of land on the Moapa River Indian Reservation within a 6,000-acre study area. The proposed action would also include the installation of a battery energy storage system and the construction of access roads and overhead collector lines to tie the projects into the regional electrical grid at a previously approved substation.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete