US 275 West Point to Scribner
PROJECT WEBSITE: Environmental Impact Statement - US Highway 275
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/24/2024
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
Other Projects
LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Regulatory
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Civil Works
Department of the Interior, Fish and Wildlife Service
Department of Agriculture, Natural Resources Conservation Service
Description:
Nebraska DOT proposes to use state funds to expand US 275 from a two-lane highway to a four-lane expressway along an approximately 20-mile segment from northwest of West Point to southeast of Scribner, including a bypass around Scribner, in Cuming and Dodge Counties, Nebraska.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|