USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

West of Devers Upgrade (CACA-55285)

PROJECT WEBSITE: http://www.blm.gov/ca/st/en/fo/palmsprings/transmission/WestOfDeversProject.html

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/07/2017

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Electricity Transmission

SECTOR
Electricity Transmission

Project Category

CATEGORY
Project Category Other Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior

Description:

The West of Devers Upgrade Project as proposed by SCE includes the following major components:

  • Removal and upgrade of existing 220 kV transmission lines. Upgrades would occur on 30 miles of the Devers–El Casco line, 14 miles of the El Casco–San Bernardino line, 43 miles of the Devers–San Bernardino line, 45 miles of the Devers-Vista No. 1 and No. 2 lines, 3.5 miles of the Etiwanda–San Bernardino line, and 3.5 miles of the San Bernardino-Vista line.
     
  • Upgrade substation equipment at Devers, El Casco, Etiwanda, San Bernardino, and Vista Substations to accommodate increased power transfer on 220 kV lines.
     
  • Upgrade Timoteo and Tennessee 66/12 kV substations to accommodate 66 kV subtransmission line relocations.
     
  • Removal and relocation of 2 miles of two existing 66 kV subtransmission lines.
     
  • Removal and relocation of 4 miles of existing 12 kV distribution lines.
     
  • Installation of telecommunication lines and equipment for the protection, monitoring, and control of transmission lines and substation equipment.

The Proposed Project would be located within the existing West of Devers right-of way corridor in incorporated and unincorporated areas of Riverside and San Bernardino Counties. The ROW passes through the reservation trust land of the Morongo Band of Mission Indians and the cities of Banning, Beaumont, Calimesa, Colton, Grand Terrace, Loma Linda, Palm Springs, Rancho Cucamonga, Redlands, San Bernardino, and Yucaipa.  SCE states that the Proposed Project would be operational by 2020.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete