San Francisco Downtown Ferry Terminal Expansion Project

PROJECT WEBSITE: Downtown San Francisco Ferry Terminal Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/22/2014

7 out of 7

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Transit Administration

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Interior

Department of the Interior, Fish and Wildlife Service

No icon

States

No icon

Department of Defense, US Army Corps of Engineers - Regulatory

Description:

The Downtown San Francisco Ferry Terminal expansion project would improve waterside and landside facilities at the city's busy Ferry Terminal. The project, managed by the San Francisco Bay Area Water Emergency Transportation Authority, is proposed to expedite boarding for more than 10,000 daily passengers, provide better access to jobs and entertainment centers downtown, and improve connections to area pedestrian, bicycle, and transit facilities. Ferry Terminal improvements will also expand the region's ability to provide vital transportation services in the event of an emergency.

 

*This project was identified Regionally or Nationally Significant in the original Permitting Dashboard

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete