FAST-41 Postings by Agencies for Seminoe Pumped Storage Project

Federal Energy Regulatory Commission (Posted on: )

Application and Supporting Documents

The project sponsor filed an application for an original license on January 18, 2023.  The application and other supporting documents can be found by searching under docket number P-14787 in the Commission’s eLibrary system.

Information on the status of mitigation measures

On September 26, 2025, the Commission issued a draft Environmental Impact Statement discussing proposed and recommended environmental measures for the proposed project. 

Description of the status of any litigation

There is no active litigation on the Commission’s licensing proceeding.

Information about project-related public meetings, public hearings, and public comment periods

Information on the timing of project-related comment periods and public meetings will be added to this section as it becomes available. 

  • On September 6, 2024, the Commission issued a notice establishing a deadline for filing scoping comments, and providing information on public scoping meetings and an environmental site review.
  • On January 13, 2025, the Commission issued a notice establishing a deadline for filing comments, recommendations, terms and conditions, and prescriptions. 
  • On March 28, 2025, the Commission issued a notice establishing a deadline for filing additional comments on the scope of issues to address in the Environmental Impact Statement.
  • On September 26, 2025, the Commission issued a notice with information on submitting written comments and attending public comment sessions on the draft Environmental Impact Statement.  
  • On January 23, 2026, the Commission issued a notice extending the comment period on the draft Environmental Impact Statement.
Description of any Federal agency action taken or decision made that materially affects the status of the project

Bureau of Land Management (Posted on: )

FAST-41 Initiation Notice

FAST-41 Initiated February 2, 2023

Contact Lead Agency (FERC) Project Manager for additional information.

Application and Supporting Documents

Applications: WYWY 191971, WYWY 191971-01, WYWY 191971-02

Contact BLM Project Manager for additional information.

BLM Rawlins Field office contact for the right-of-way is Carla Fiedor, her email is c75fiedo@blm.gov, phone number (307) 328-4251.

BLM Rawlins Field office contact for planning/NEPA is Wendy Huber, whuber@blm.gov, phone number (307) 775-6288.

Information on the status of mitigation measures

BLM must solicit information about key mitigation measures during the public comment period that follows the NOA for the Draft EIS. BLM will also continue to consider possible mitigation measures through internal and external scoping throughout the planning process. Resource areas that BLM has currently identified as requiring possible mitigation include:

  • Removal of Limber Pine
  • Big Game Winter Crucial Range – Determination on mitigation measures will require coordination with the Wyoming Game and Fish Department
  • BLM Threatened & Endangered or Sensitive Species
  • Visual Impacts in Visual Resource Management Avoidance Areas (Class II VRM)

A document outlining mitigation measures necessary for wildlife from the Rawlins RMP is attached for reference.

BLM must solicit information about key mitigation measures during the public comment period that follows the NOA for the Draft EIS. BLM will also continue to consider possible mitigation measures through internal and external scoping throughout the planning process. Resource areas that BLM has currently identified as requiring possible mitigation include:

·       Removal of Limber Pine

·       Big Game Winter Crucial Range – Determination on mitigation measures will require coordination with the Wyoming Game and Fish Department

·       BLM Threatened & Endangered or Sensitive Species

·       Visual Impacts in Visual Resource Management Avoidance Areas (Class II VRM)

A document outlining mitigation measures necessary for wildlife from the Rawlins RMP is attached for reference.

Description of the status of any litigation

N/A

Information about project-related public meetings, public hearings, and public comment periods

Tribal Outreach: EIS effort should include Historic Properties Treatment Plan for the BLM ROW. If it does not, further coordination with BLM will be required. Typically the EIS would include a Programmatic Agreement as an appendix, which would contain the Historic Properties Treatment Plan.

Cooperating Agency Meetings: Will FERC identify local governments with jurisdiction by law or special expertise that should be Cooperating Agencies and schedule the necessary Cooperating Agency meetings that include these entities? BLM can provide support/advice. BLM usually conducts Cooperating Agency meetings on a regular (e.g., monthly) basis, or at a minimum after each EIS stage (I.e., pre-NOI, NOI, Draft EIS NOA, Final EIS NOA, ROD).

Socioeconomics Workshop: BLM conducts at least one Socioeconomics Workshop during the NOI scoping period. BLM could likely do this in cooperation with FERC if FERC already plans to host a workshop(s)

Public Scoping Meetings: BLM conducts at least one public scoping meeting during the 30-day scoping period that follows the NOI. BLM could likely do this in cooperation with FERC if FERC already plans to host a meeting(s)

Action:  Environmental Impact Statement (FERC)

              Milestones:

Issuance of Notice of Intent to Prepare an EIS (Agency Action):  02/25/2025

Conduct 30-day scoping period (43 CFR 1610.2(e)) (Agency Action):  02/25/2025

Official Notice of Availability of a Draft EIS published in the FR (Agency Action):  08/29/2025

Conduct 90-day public comment period (43 CFR 1610.2(e)) (Agency Action):  no date set

Official Notice of Availability of a Final EIS published in the FR (Agency Action):  03/13/2026

Issuance of Lead Agency Record of Decision (Agency Action):  06/18/2026

Action:  Environmental Impact Statement (BLM)

Milestones:

Adopt FERC Final EIS (Cooperating Agency Action): 06/25/2026

Conduct 30-day Protest Period (43 CFR 1610.5) (Cooperating Agency Action): 07/25/2026

Conduct 60-day Governor’s Consistency Review (43 CFR 1610.3 2(e)) (Cooperating Agency Action): 08/25/2026

Issue Record of Decision (Cooperating Agency Action): 09/25/2026

 

 

Description of any Federal agency action taken or decision made that materially affects the status of the project

BLM will likely have to amend our Rawlins Resource Management Plan to issue the required Rights-of-Way.

Fish and Wildlife Service (Posted on: )

FAST-41 Initiation Notice

FERC has posted the FAST-41 Initiation Notice.

Application and Supporting Documents

None at this time.

Information on the status of mitigation measures

None at this time.

Description of the status of any litigation

NA

Information about project-related public meetings, public hearings, and public comment periods

FWS has no information at this time.

Description of any Federal agency action taken or decision made that materially affects the status of the project

None at this time.

US Army Corps of Engineers - Regulatory (Posted on: )

FAST-41 Initiation Notice

Lead agency will provide FIN

Application and Supporting Documents

USACE received a request for a Department of the Army Permit on September 28, 2023.

Information on the status of mitigation measures

The Corps requires that applicants consider and use all reasonable and practical measures to avoid and minimize impacts to aquatic resources. If the applicant is unable to avoid or minimize all impacts, the Corps may require compensatory mitigation. The applicant has proposed to pursue mitigation approaches which may consist of either mitigation banking or “in lieu fee,” in which any such mitigation approaches would be developed in coordination with federal agencies.  In any case, unavoidable impacts to aquatic resources, and resulting adverse effects to the aquatic environment, would be offset via compensatory mitigation and would comply with the 2008 Mitigation Rule. 

Description of the status of any litigation

N/A

Information about project-related public meetings, public hearings, and public comment periods

FERC hosted public scoping meetings in 2024.  USACE has not hosted a pubic hearing or meeting in association with the DA permit review. 

Description of any Federal agency action taken or decision made that materially affects the status of the project

A 30-day public notice was published on October 16, 2023.  The notice is available here: extension://efaidnbmnnnibpcajpcglclefindmkaj/https://usace.contentdm.oclc.org/utils/getfile/collection/p16021coll15/id/3463 

Bureau of Reclamation (Posted on: )

FAST-41 Initiation Notice

The Lead Agency will post the FIN.

Application and Supporting Documents

The Bureau of Reclamation (Reclamation) published a Federal Register Notice to solicit proposals for the development of a non-Federal hydropower at Seminoe Reservoir (Federal Register :: Pumped-Storage Hydroelectric Power Development on Seminoe Reservoir, Kendrick Project, Wyoming). 

In response to the Federal Register Notice, Reclamation received an application from Black Canyon Hydro. The application contains proprietary information and is not available for posting.

Reclamation selected Black Canyon Hydro and entered into a preliminary lease of power privilege on February 23, 2021.

Information on the status of mitigation measures

A portion of the mitigation measures will be determined in the Record of Decision at the end of the environmental review process.  The remainder of the mitigation measures will be determined through the lease of power privilege process and will be based on actual construction methods and proximity to Seminoe Dam.

Description of the status of any litigation

None.

Information about project-related public meetings, public hearings, and public comment periods

All public engagement activities will occur through the NEPA process; see FERC's Environmental Impact Statement action for general public engagement opportunities.  

Description of any Federal agency action taken or decision made that materially affects the status of the project

Refer to the Application and Supporting Documents section above.