(TX) IH-35 at Red River

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/22/2020

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Texas

LEAD AGENCY
Texas

Description:

The Texas Department of Transportation (TxDOT) is proposing to widen a 22 mile section of Interstate Highway 35 (IH 35) in Love County, Oklahoma and Cooke County, Texas. The project corridor is located in Love County, Oklahoma and Cooke County, Texas and passes through the municipalities of Gainesville and Valley View, between Interchange 1 in southern Oklahoma and Farm-to-Market Road (FM) 3002 in southern Cooke County.  The purpose of the project is to make improvements to upgrade IH 35 to current design standards, address safety concerns, and provide for future traffic needs (2030). 

The proposed improvements to IH 35 would ultimately include widening the roadway to eight-lanes (four-lanes in each direction) predominately following the existing alignment; however, the project would initially be widened to six-lanes (three-lanes in each direction).

Transportation improvements are needed on IH 35 to address facility geometric deficiencies and projected traffic demands.  

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete