Wilmington, NC Rail Realignment Project

PROJECT WEBSITE: https://railroads.dot.gov/environment/environmental-reviews/wilmington-nc-rail-…

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/30/2022

0 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Railroad Administration

Description:

The Wilmington Rail Realignment Project (Project) is located primarily within the City of Wilmington and New Hanover County, but also extends into Brunswick County. The existing CSXT rail line, commonly referred to as the “Beltline,” is the only active track through the City. The Project proposes to reroute all existing freight traffic (both local and through traffic) from the Beltline to a new rail connection to be constructed between Davis Yard/Navassa and the Port of Wilmington. The Project will improve safety, regional transportation mobility, and freight rail operations, while also improving the resiliency, reliability, and operational fluidity of the sole freight rail route connecting southeastern North Carolina with the Port of Wilmington. Currently the Project is unfunded.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete