YOL 80 Bus/Carpool lanes
PROJECT WEBSITE: https://dot.ca.gov/caltrans-near-me/district-3/d3-projects/d3-i80-corridor-impr…
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/01/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Department of the Army, US Army Corps of Engineers - Regulatory
Description:
The California Department of Transportation (Caltrans), in collaboration with stakeholders, proposes to construct improvements consisting of managed lanes, pedestrian/bicycle facilities, and Intelligent Transportation System (ITS) elements along Interstate 80 (I-80) and United States Route 50 (US-50) from Kidwell Road near the eastern Solano County boundary (near Dixon), through Yolo County, and to West El Camino Avenue on I-80 and Interstate 5 (I-5) on US-50 in Sacramento County.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|