16th Street Mall Improvements Environmental Assessment
PROJECT WEBSITE: The Mall Experience
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/25/2019
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Transit Administration
Description:
The City and County of Denver, Regional Transportation District, Downtown Denver Partnership, and Federal Transit Administration (Project Partners) have completed the 16th Street Mall Environmental Assessment (EA), which identifies a Preferred Alternative to reconstruct the 16th Street Mall between Market Street and Broadway. The project plans include reconstructing the historic 16th Street Mall to address infrastructure, mobility, safety, and public use needs. The project will install a new granite paver system with improved surface friction and proper drainage. The spatial reconfiguration will create wider pedestrian areas with trees on both sides of each block. Transit lanes would be consolidated in the center of the Mall, and the Free MallRide service would continue.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|