Alkali Creek Reservoir Project

PROJECT WEBSITE: Alkali Creek Reservoir Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/31/2021

5 out of 5

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Water Resources

SECTOR
Water Resources

Project Category

CATEGORY
Project Category Other Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

Other Agencies with Actions or Authorizations:

No icon

Wyoming

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Description:

The State of Wyoming Water Development Commission (WWDC) proposes to construct a 294-acre reservoir on Alkali Creek and ancillary facilities across public and private land near Hyattville, Wyoming. The reservoir would impound approximately 7,994 acre-feet of water under normal conditions, and 9,872 acre-feet when under flood conditions. The reservoir would provide late-season irrigation water for portions of the Nowood River Watershed. The irrigation pool would be available either directly or through exchange for irrigation water.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete