Dot gov

The .gov means it’s official.
Federal government websites often end in .gov or .mil. Before sharing sensitive information, make sure you're on a federal government site.

SSL

The site is secure.
The https:// ensures that you are connecting to the official website and that any information you provide is encrypted and transmitted securely.

American Airlines Campus Redevelopment Project in Fort Worth Texas, Environmental Assessment

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Cancelled icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
CANCELLED

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
N/A

0 out of 0

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Aviation icon

SECTOR
Aviation

CATEGORY
DOT Projects

Department of Transportation icon

LEAD AGENCY
Department of Transportation, Federal Aviation Administration

Description:

The proposed Project will be completed in two development phases, and include the demolition, reconstruction and rehabilitation of multiple buildings and associated infrastructure located on parcels on the west side of State Highway (SH) 360 between SH 183 and Trinity Boulevard in Fort Worth, Texas on DFW Airport property.

Project was cancelled since the FAA no longer has an action as a result of the new FAA reauthorization act.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete