Broadway Bridge Construction
PROJECT WEBSITE: Broadway Bridge Project
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/20/2033
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Other Agencies with Actions or Authorizations:
Department of Commerce, National Oceanic and Atmospheric Administration
California
Department of the Interior, Fish and Wildlife Service
Department of Homeland Security, US Coast Guard
Description:
The City of West Sacramento, in cooperation with the City of Sacramento and Caltrans, proposes to construct a new bridge over the Sacramento River downstream of the U.S. 50 Pioneer Bridge, connecting South River Road and 15th Street to the Broadway corridor. Several bridge alignment alternatives are being considered as part of the project. The new bridge will be moveable to allow boat passage and will carry vehicular, bicycle and pedestrian traffic, and accommodate future transit options, including a future streetcar alignment within the bridge itself. The project also includes installation of a bridge interconnect fiber optic line to allow the new bridge, and I Street and Tower Bridges, to be operated by one system.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|