FM 1461

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/07/2019

2 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation icon

SECTOR
Surface Transportation

CATEGORY
DOT Projects

Texas icon

LEAD AGENCY
Texas

Description:

The purpose of the proposed project is to provide a facility that would accommodate expanding transportation demands resulting from population growth and economic development in the region; increase mobility and accessibility in the region; and to provide an east-west transportation facility to serve the communities in the project area. The proposed project includes the reconstruction and widening of FM 1461 from SH 289 to County Road 123. The proposed project is located in Collin County, surrounded by communities of McKinney, Prosper, and Celina. Proposed improvements would involve the expansion from a two-lane rural highway to a four-lane urban highway. Expansion would consist of one 12-foot wide travel lane and one 14-foot wide outside shared-use lane in each direction, a proposed median to accommodate future ultimate six-lane facility, and sidewalks located along the outside of both the eastbound and westbound lanes. The existing right-of-way (ROW) width is 90 feet and will increase with the proposed project. The proposed ROW is anticipated to acquire approximately 58 acres to expand the roadway, based on this preliminary level of design. No residential or non-residential displacements are anticipated.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete