Dot gov

The .gov means it’s official.
Federal government websites often end in .gov or .mil. Before sharing sensitive information, make sure you're on a federal government site.

SSL

The site is secure.
The https:// ensures that you are connecting to the official website and that any information you provide is encrypted and transmitted securely.

FM 1516

PROJECT WEBSITE: FM 1516

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Class of Action Changed icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
CLASS OF ACTION CHANGED

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
N/A

1 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation icon

SECTOR
Surface Transportation

CATEGORY
DOT Projects

Texas icon

LEAD AGENCY
Texas

Description:

TxDOT proposes improving FM 1516 by expanding the two-lane road to a four-lane road with a center left turn lane. The proposed project also includes adding a sidewalk and bike lane and realigning the intersection of FM 1516 at FM 1976.

Proposed Improvements

  • Expanding the current road to four 11-foot travels lanes (two lanes in each direction)
  • Constructing one 12-foot center turn lane
  • Adding two 5-foot bike lanes (one bike lane in each direction)
  • Adding sidewalks on each side of the road

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete