Lake Powell Pipeline

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Paused

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PAUSED

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

1 out of 6

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Water Resources

SECTOR
Water Resources

Project Category

CATEGORY
Project Category Other Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Reclamation

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Interior

Department of the Interior, Bureau of Land Management

Department of the Interior

Department of the Interior, National Park Service

Department of the Interior

Department of the Interior, Bureau of Indian Affairs

Description:

The LPP is a proposed 140-mile, 69-inch-diameter water delivery pipeline that begins at Lake Powell near Glen Canyon Dam in Page, Arizona, and ends at Sand Hollow Reservoir near St. George, Utah. The pipeline would deliver up to 86,249 acre-feet of water from Lake Powell to Sand Hollow Reservoir. UBWR proposes building the LPP in order to establish a second source of water to Washington and Kane Counties in Utah to meet future water demands, diversify the regional water supply portfolio, and enhance the reliability of the water supply. Two pipeline alignments have been proposed: the Southern Alternative and the Highway Alternative. Both alternatives begin and end in the same locations. The Southern Alternative would travel south of the Kaibab Indian Reservation. The Highway Alternative would cross lands held in trust by the United States for the benefit of the Kaibab Band of Paiute Indians, following Arizona State Route 389. Both proposed alternatives would cross federal, state, private, and tribal trust lands. In addition, UBWR has requested a water exchange contract with Reclamation wherein UBWR would forbear the diversion of a portion of the natural flows to which UBWR is entitled in exchange for depleting an equal amount of water released from Flaming Gorge Dam throughout the year and available at Lake Powell. This exchange contract would not entitle UBWR to call for releases from Flaming Gorge.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete