MVP Southgate CP19-14
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
							ENVIRONMENTAL REVIEW AND PERMITTING STATUS
							IN PROGRESS
						
																																				ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
																																06/18/2020
																					
							ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
							COMPLETED
						
								SECTOR
								Pipelines
							
							CATEGORY
																						
								Project Category
              Other Projects
																				
								LEAD AGENCY
																	Federal Energy Regulatory Commission
															
Other Agencies with Actions or Authorizations:
Federal Energy Regulatory Commission, Office of Energy Projects
Department of the Interior, Fish and Wildlife Service
Description:
On June 18, 2020, the Commission issued a certificate order in Docket No. CP19-14-000 authorizing the project sponsor to construct and operate the MVP Southgate Project, including approximately 75.1 miles of natural gas pipeline and associated aboveground facilities in Pittsylvania County, Virginia, and Rockingham and Alamance Counties, North Carolina. On February 3, 2025, the project sponsor filed an application in Docket No. CP25-60-000 requesting to amend the certificate for the MVP Southgate Project issued by the Commission in Docket No. CP19-14-000.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
 
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
 - Responsible Agency:
 - Bureau:
 - Action Status:
 - SHPO:
 - Action Identifier:
 - Action Outcome:
 
| Milestone | Original Target Date | Current Target Date | Milestone Complete | 
|---|