(TX) SH 286 (FM 43 to FM 2444)

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/01/2022

2 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation icon

SECTOR
Surface Transportation

CATEGORY
DOT Projects

States icon

LEAD AGENCY
States, Texas

Description:

The Build Alternative would include widening the existing 2-lane undivided highway to a controlled access four-lane freeway with two 12-foot main lanes in each direction, the main lanes having four-foot inside shoulders and 10-foot outside shoulders, two 12-foot frontage road lanes in each direction with a 12-foot outside shoulder, entrance and exit ramps, and five-foot sidewalks outside the frontage road shoulders. The proposed improvements would include grade separations at CR 20A, CR 22, and FM 2444. The project length, including all transitions, is approximately 3.2 miles.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete