Attentive Energy Two Offshore Wind Project
PERMITTING DASHBOARD PROJECT POSTING DATE: NOVEMBER 08, 2024All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/19/2028
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of Commerce, National Oceanic and Atmospheric Administration
Department of the Interior, Fish and Wildlife Service
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Army, US Army Corps of Engineers - Civil Works
Environmental Protection Agency
Description:
Attentive Energy LLC proposes to develop an offshore renewable wind energy facility to generate 1,545 megawatts of energy in the western portion of Bureau of Ocean Energy Management’s Lease Area Outer Continental Shelf (OCS)-A 0538. OCS-A 0538 is located approximately 68 kilometers (36 nautical miles) offshore from the nearest shoreline point in New Jersey and 87 kilometers (47 nautical miles) from the nearest shoreline point in New York. The wind energy facility would include wind turbine generators, foundations, inter-array cables, and one offshore substation with capacity for an offshore transmission network or one offshore substation and a stand-alone offshore transmission network platform with an independent foundation, offshore export cable, onshore export cables, and an onshore converter station to connect to the Larrabee Collector Station, a substation in Howell Township, New Jersey.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|